Riley, C.
Targeted liquid injection improves shed deck performance
Process Optimization
/ Project Management
/ Refining
/ Americas
/ Asia/Pacific
/ Distillation
/ Economics
/ Engineering & Design
/ Equipment
/ Europe
/ Heat Transfer
/ Management
/ Middle East
This case study shows how the installation of an unique piping and lance design achieved targeted liquid injection, quenched vapor hot zones and reduced resid entrainment into the heavy coker gasoil product.
- 1
- ... 1 pages
Current Digital Edition
Sign up to Receive Our Newsletter
Latest News
- Iraq increases domestic refining capacity by 360,000 bpd within the past year 5/6
- UAE's Mubadala Capital plans $13.5-B biofuels investment in Brazil 5/6
- Liquid Wind's second eFuel facility granted environmental permit 5/6
- BASF and IPP jointly market the sale/relocation of three plants from Verbund site in Germany 5/6
- Clariant introduces new solutions to reduce the environmental impact of plastics 5/6
- Singapore Airlines Group orders sustainable aviation fuel from Neste 5/6
Construction Boxscore: Project Spotlight
Project:
Long Son Petrochemicals Complex
Location:
Long Son, Vietnam
Operator:
Siam Cement Group
Cost:
$5.4 B
Capacity:
1.65 MMtpy
Completion date:
2023
Status:
Under Construction