A gas processing plant in Malaysia eliminated a source of expensive failures in its acid gas removal unit (AGRU).
Improve pump reliability with advanced composite wear rings
The results were reduced vibration and seal leaks at this plant
Improving equipment reliability through e-learning
It will change the way people work, learn, communicate and solve problems
- 1
- ... 1 pages
Current Digital Edition
Sign up to Receive Our Newsletter
Latest News
- Shell flags chemicals and products unit loss, raising doubts over $3.5 B buyback 1/8
- Saudi's SABIC sells assets in Europe, Americas worth $950 MM 1/8
- Outokumpu to collaborate with Norsk e-Fuel to convert carbon side streams into eSAF 1/8
- Haffner Energy and IGNIS P2X launch bio/eSAF project AeroVerde in Spain 1/8
- Faerch advances circular packaging leadership with growing rPET volumes from Cirrec 1/8
- Aether Fuels receives millions of additional funding to accelerate SAF production in Singapore 1/8
Construction Boxscore: Project Spotlight
Project:
Long Son Petrochemicals Complex
Location:
Long Son, Vietnam
Operator:
Siam Cement Group
Cost:
$5.4 B
Capacity:
1.65 MMtpy
Completion date:
2023
Status:
Under Construction