Cenovus refinery in Ohio (U.S.), plans to shut multiple units for 6 weeks for maintenance
3/31/2025 2:00:00 PM
Cenovus will begin planned maintenance work on multiple units at its 160,000-barrel-per-day refinery in Toledo, Ohio in mid April.
Roughly a third of the facility will be down for maintenance as early as the second week of April, the source said. The refiner's reformer, hydrotreater, hydrocracker, crude unit and coker unit will undergo maintenance.
The planned work is expected to last around six weeks.
The Toledo refinery can produce around 3.8 million gallons of gasoline, 1.3 million gallons of diesel fuel and 600,000 gallons of jet fuel per day.