Magnolia LNG picks SK for technical services work
4/14/2014 12:00:00 AM
Australia-based Liquefied Natural Gas subsidiary Magnolia LNG has executed a technical services agreement with SK Engineering and Construction Co. (SKEC Group).
The deal relates to the ongoing engineering, procurement and construction (EPC) activities for MLNGs planned 8 million tpy Magnolia LNG project in Lake Charles, Louisiana.
Under the agreement, the SKEC Group will, among other things:
- Continue to review all pre-front end engineering design (FEED) information and data included in the preliminary resource reports submitted to the Federal Energy Regulatory Commission (FERC).
- Assist MLNG to complete the final resource reports as part of MLNGs filing application to FERC, which is targeted for submission by the end of April 2014.
, - Complete the FEED for the Magnolia LNG project including gas pre-treatment facilities, 4 LNG trains (each with nominal LNG production capacity of 2 million tpy),2 x 160,000 cubic meter full containment storage tanks, jetty and ship loader facilities and all related infrastructure and services.
- Prepare a detailed lump sum turn-key (LSTK) EPC cost estimate on an open book basis by November 28, 2014.
- Negotiate and agree with MLNG a detailed LSTK EPC contract term sheet, which is targeted for completion by June 30, 2014.
- Negotiate and agree a definitive and binding LSTK EPC contract based on the term sheet.
The SKEC Group says it has been progressing for some time on several of the above activities under a shorter-term letter of engagement, which is now superseded by the this agreement.
In addition, the SKEC Group has already completed a satisfactory detailed review of the OSMR process technology, which will be employed in the Magnolia LNG project, and provided the company with an initial estimated EPC cost of $1.57 billion, which was consistent with the budget estimate, including appropriate contingencies.
Comments